The two wells will meet the remaining exploration requirements as per the exploration licences issued by the Ministry of Energy and Minerals (MEM). Shell became the operator of the two blocks in February 2016, after its combination with BG Group, and has been working closely with the Tanzania Petroleum Development Corporation (TPDC) and MEM to deliver these wells safely.

The development of Blocks 1 and 4 is part of the Tanzania LNG project, which is a critical part of Tanzania’s national energy policy under the umbrella of the Vision 2025.

Shell and its Block 1 and 4 partners are working with TPDC and other Block 2 partners on future development of Tanzania LNG. The project is being developed at a time of great industry change and historic low oil prices. In the current investment climate, there is a critical need to have strong project fundamentals, including government support and cooperation.