With further wells being brought back online in recent days, production has increased to 8000 bpd. This figure includes some flush production, and it is expected that average Montara production will return to pre-shutdown levels of 6000 bpd over the coming days. Ballast water tank 4P has also been returned to service following completion of final inspections and repairs. Preparations for the repair of the previously reported defect between oil cargo tank 5C and ballast water tank 4S are underway and additional inspections in tank 4S are ongoing. The company will now utilise a smaller and lower cost shuttle tanker to provide additional storage during a period of time when the FPSO storage capacity is constrained.