Drilling operations will commence as soon as the site has been cleared and levelled, and the rig is in the Field.
Well H18E N4, which is expected to be designated GY-682, is targeting a net 200 ft thick Mayaro Sandstone pay interval at a depth between 300 and 1000 ft depth and the well is anticipated to be completed for production immediately after drilling operations are concluded. Rig#18 will then be moved to the second planned location, H18E G11(5).
Neil Ritson, LGO's Executive Chairman, commented:
"A delay beyond our immediate control caused some minor slippage in the timing of the planned drilling programme, however, we are very pleased that work is now underway. These wells are the first two on a renewed campaign of production well drilling and we are pleased to be able to return to normal operations and to the multi-year development plan we have had in place at Goudron since its acquisition in 2012."




